Civil>Crane>SINGLE STOREY OVERHEAD PLATFORM  
SINGLE
STOREY OVERHEAD PLATFORM
Usually erection
of scaffolds will be handled by contractor, but it will be an advantage for us
to understand the correct methods of erecting scaffolding. Improper erection may
result to a serious injury to the workers and damage to the equipment. A
single storey (stage) overhead platform (STIP) is commonly erected with reason
for the worker to work on such equipment at height beyond ground reach of
between 6 feet to 12
feet. This platform is needed for us to do work or maintenance comfortably.(i.e.
Like overhead valves, high switches beside vessels, high pipeline flanges ).
If the equipment is higher then 12 feet, (which is more then twice to the
average human height), a multi stage scaffolds need to be raise.
1. Ensure spaces between platform transoms does not exceed the following:
a. 990mm (3 feet) space for 32mm (1.3 inch) board (plank) thickness.
b. 1520mm (5 feet) for 38mm (1.5 inch) board thickness.
c. 2600mm (8.5 feet) for 50mm (2 inch) board thickness.
2. Ensure the gaps between board (planks) do not exceed 25 mm (1 inch).
3. Install Toe board above the planks, basically to prevent tools or materials
place on the
planks form dropping to ground.
4. Only select good scaffolding tubes for the structure frame work, discard
dented tube.
5. Use swivel or double coupler on the right place.
6. Use Base plate (planks) , to prevent scaffolds footers from sinking or
tilting.
7. Diagonal or Transverse or Longitudinal brace are used to strengthen the
structure
frame of the scaffolds. Transverse brace is fitted on every lift needed (about 6
feet
ht.)
8. Install ladder to easy access to the platform floor, ladder must be properly
secured
vertically along the scaffolds structure and extend at least 1M (3 feet) above
the
working platform.
9. Ensure that Guardrail are fitted at height of between 920mm to 1150mm ( 3 to
4 feet).
To protect worker from falling and for the workers to hook their safety harness.
|
|
Mobile
Crane Inspection Guidelines for OSHA Compliance
Officers
Although some crane inspection checklist items
are self-explanatory, Observing crane operations
prior to an inspection, or asking questions
about how it Crane Inspection Services. - Crane
Operator Training, Crane Crane Inspection
Services provides accredited crane operator
training, crane inspection, load testing,
overhead rigging training, crane accident ...
www.craneinspection.com
Crane Management - Home
Port of Miami Crane Management, Inc., (Crane
Management) a company created ... Crane
Management recorded 1.01% overall downtime in
fiscal Crane Management :: Home
[Crane Management description] Crane
Aboriginal Management Services (CAMS) is a 100%
Native owned company with experience in business
plan preparation Sparrows Offshore - Offshore
Crane Management, Operation The world's largest
offshore crane management, lifting and
mechanical handling contractor, encompassing
engineering, design, manufacture, operation, ...
www.sparrowsoffshore.com
CMS2000™ Crane
Management System - Product Information
CMS2000™ Crane Management System. Status
displays. Production logging. Fault logging.
System Diagnostics. Maintenance Management.
Remote Diagnostics Crane Management Awareness
bullet. Crane Management Workbook. bullet. Crane
Safety Reference Card. bullet. Rigging Safety
Reference Card. bullet. Hoisting Personel Safety
Reference ...
www.craneinstitute.com
Riggers Page
Ratings charts and usage information
for a variety of theatrical rigging hardware.
www.rigging.net/ -
Aerial Delivery - Army Quartermaster Parachute
Riggers Airborne Aerial Delivery & Army Rigger
History Page. Career: Riggers The Internet
System for Education and Employment Knowledge (ISEEK)
is Minnesota's website for career exploration,
education and training, employment and
Brion Toss Yacht Riggers, Sailboat Rigging This
website is an outgrowth of both rigging and
teaching; in the following pages you'll find
field-proven tools and ideas powerful and
elegant enough
www.briontoss.com
Riggers Manufacturing
Company
RIGGERS MANUFACTURING COMPANY produces
top-of-the-line equipment for lifting and
transporting heavy loads in confined and
exacting situations. Summary Report
49-9096.00 - Riggers. Set up or repair rigging
for construction projects, manufacturing plants,
logging yards, ships and shipyards, or for the
entertainment Amazon.com: Technical Rescue
Riggers Guide: Books: Rick Lipke Amazon.com:
Technical Rescue Riggers Guide: Books: Rick
Lipke by Rick Lipke.
www.amazon.com
Riggers
49-9096 Riggers. Set up or repair rigging for
construction projects, manufacturing plants,
logging yards, ships and shipyards, or for the
entertainment Rigging certificates Anyone
intending to undertake field work using riggers
should purchase a copy of the Safety Information
Handbook outlining the requirements for safety
ETCP - The Entertainment Technician
Certification Program
ETCP is proud to announce the first ETCP
Certified Riggers! Congratulations to the
riggers who have made this important
professional commitment to ...
etcp.esta.org/cert |
|
|
Find What You Are
Looking For? |
|
Can't
find the one you're looking for?
Search our database of over 1, 000, 000
Information |
|
Quick
Search |
|
Assist us in keeping
this site ONLINE by adding to your
Bookmarks!!
Thank you for your
support |
| |
|
©2007-2020 Intro2U.COM. All
rights reserved. Intro2U.COM and its Contents are registered trademarks of
Intro2U.COM
The Introduction Search Engine, The Introduction Web, The Introduction Toolbar
and Design Info are service marks of Intro2U.COM
No portion of this site may be copied, retransmitted, reposted, duplicated or
otherwise used
without the express written permission of Intro2U.COM
|